9 workers finish a job in 9 days. How long will 18 workers take?

Practice this MCQ with options, instant answer checking, explanation, exam-wise filters, next/previous navigation and shareable result image.

Question ID #20202

9 workers finish a job in 9 days. How long will 18 workers take?

Correct Answer: D. 4.5 days

9 workers finish a job in 9 days. How long will 18 workers take? - MCQ Explanation

This question is useful for exam preparation because it provides direct multiple-choice practice with options, answer checking and explanation.

Correct answer: D. 4.5 days