8 workers finish a job in 11 days. How long will 16 workers take? Apply it in the context of AFCAT Percentage Ratio Profit and Interest Test.

Practice this MCQ with options, instant answer checking, explanation, exam-wise filters, next/previous navigation and shareable result image.

Question ID #21880

8 workers finish a job in 11 days. How long will 16 workers take? Apply it in the context of AFCAT Percentage Ratio Profit and Interest Test.

Correct Answer: D. 5.5 days

8 workers finish a job in 11 days. How long will 16 workers take? Apply it in the context of AFCAT Percentage Ratio Profit and Interest Test. - MCQ Explanation

This question is useful for exam preparation because it provides direct multiple-choice practice with options, answer checking and explanation.

Correct answer: D. 5.5 days